Zimbabwe power utility says network overhaul needs US$2.4 billion
ZETDC says two decades of underfunding left transmission and distribution assets short of maintenance, refurbishment and expansion.
Zimbabwe Electricity Transmission and Distribution Company (ZETDC) needs US$2.4 billion to rehabilitate Zimbabwe’s electricity transmission and distribution network, senior manager John Diya said in Harare. He made the estimate at the launch of the State of the Mining Industry Report.
Diya said the tariff averaged two cents per kilowatt hour for 20 years, while electricity procurement cost 9.8 cents. The resulting funding gap left the utility unable to maintain, refurbish or expand its network, contributing to frequent breakdowns for consumers. A completed audit identified stations needing additional lines and transformers, he said.
Diya said generation was adequate, but Kariba output is set to fall to an average of 300 megawatts in January 2027 and 250 megawatts in February and March, from 530 megawatts now. Hwange Units 7 and 8, supplying 600 megawatts, are scheduled to return from maintenance on 4 January and 25 January.
Why it mattersElectricity consumers are experiencing frequent breakdowns as ZETDC works to address network needs valued at US$2.4 billion.